days taken for a piece of work

Post a reply

Smilies
:D :) :( :o :shock: :? 8) :lol: :x :P :oops: :cry: :evil: :twisted: :roll: :wink: :!: :?: :idea: :arrow: :| :mrgreen:
BBCode is ON
[img] is ON
[flash] is OFF
[url] is ON
Smilies are ON
Topic review
LaTeX Help
Every formula have to stat with [tex]\textrm{[tex]}[/tex] and ends with [tex]\textrm{[/tex]}[/tex].

   
   

If you wish to attach one or more files enter the details below.

Expand view Topic review: days taken for a piece of work

Re: days taken for a piece of work

Post by rameshppc » Thu Aug 30, 2018 10:41 am

:) wow thanks a lot...
You are really great..

Re: days taken for a piece of work

Post by nathi123 » Mon Aug 27, 2018 12:32 pm

Let C finish work in x days [tex]\Rightarrow for 1 day C finish[/tex] [tex]\frac{1}{x}[/tex]of work; A finish for 1 day [tex]\frac{1}{12}[/tex]; B- for 1 day finish [tex]\frac{1}{18}[/tex]
[tex]\Rightarrow \frac{4}{12} + \frac{4}{18}+\frac{4}{x} = 1 \Leftrightarrow 3x+2x+36=9x\Leftrightarrow x=9[/tex] days.

days taken for a piece of work

Post by rameshppc » Mon Aug 27, 2018 9:59 am

A,B & C together can finish a piece of work in 4 days. A alone can do in 12 days & B alone in 18 days. How many days will taken by C to do it alone?

Pls explain how do i workout this sum?